Decision

Weydon Lane Landfill

Decision Maker: Executive

Outcome: Information Only

Is Key Decision?: Yes

Is Callable In?: Yes

Date of Decision: September 3, 2024

Purpose: Request for funds to complete works to the landfill and budget for fees to progress a larger project in the future.

Content: That the Executive approves:   1.         A project to repair the existing monitoring solution at Weydon Lane, to enable the site to be fully monitored for gas and groundwater quality, by bringing compromised vents and monitoring wells back into use. 2.         A supplementary estimate of £65,000 required for construction costs and the appointment of consultants to support the redevelopment of the site.   That the Executive endorses:   3.         The intention to redevelop the site in the long-term for recreational and leisure use.  

Supporting Documents

Report - Weydon Lane.pdf

Related Meeting

Executive - Tuesday, 3rd September, 2024 7.00 pm on September 3, 2024