Decision

Harbour Walkway

Decision Maker: Transport & Connectivity Policy Committee

Outcome: Recommendations Approved

Is Key Decision?: Yes

Is Callable In?: Yes

Date of Decision: February 6, 2025

Purpose: To seek approval for additional funding to cover the costs of a partial bank collapse and increased delivery costs, reprofile the delivery timescale and consider wider contractor costs.

Content: That the Committee for Transport and Connectivity: 1.    Approved the pausing or stopping of charging delay damages to KB and refund those levied to date (without prejudice). 2.    Accepted new funding from CRSTS over-programming (£3.5m) and EDF (£2.7m). 3.    Approved increasing the budget of the Harbour Walkway project from £3.5m to £6.2m, plus the existing £3.5m – a total of £9.7m. 4.    Approved the use of up to £3.5m of the existing project budget to negotiate an agreement with KB. 5.    Authorised the Executive Director Growth and Regeneration in consultation with the Committee Chair for Transport and Connectivity to extend/ vary the contract as necessary to enact recommendations 1 and 4. 6.    Authorised the Executive Director for Growth and Regeneration to invoke any subsequent extensions/ variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report as per recommendation 4.  

Supporting Documents

250124 Harbour Walkway budget amendment v8.pdf
Appendix B - Equality Impact Assessment - Harbour Walkway v3 SIGNED.pdf
Appendix C - Environmental Impact Assessment - Harbour Walkway.pdf