Decision
Quarter 3 Capital Monitoring Report 2024/25
Decision Maker: Cabinet
Outcome:
Is Key Decision?: No
Is Callable In?: No
Date of Decision: March 18, 2025
Purpose: Quarterly update on spend against the capital programme.
Content: Cabinet note: 1. The forecast capital expenditure for 2024/25 of £30.268M which is £7.573M lower than the latest agreed capital programme budget of £37.841M; 2. The 2024/25 significant forecast outturn variations and explanations for them as shown in section 4 of the report; 3. The quarter three forecasts and impact of scheme variances for 2024/25 on future years’ capital expenditure; 4. The latest forecast of capital receipts, grants and contributions for 2024/25 in section 5 of the report; and 5. The risks associated with the capital forecasts are as detailed in section 8 of the report.
Related Meeting
Cabinet - Tuesday, 18th March, 2025 6.30 pm on March 18, 2025