Decision
Contract Award for Herefordshire Resurfacing Works - Works Orders WO2 Programme Amendments
Decision Maker: Corporate Director – Economy & Environment
Outcome: Recommendations Approved
Is Key Decision?: No
Is Callable In?: No
Date of Decision: June 16, 2025
Purpose:
Content: To amend the works programme and agree Compensation Events, via the Works Order 2 to Tarmac Trading, using the Council’s NEC 4 Framework Agreement, to authorise an uplift of £61,220.24 to cover outstanding compensation events in relation to additional works agreed on the B4348 to the Tram Inn scheme.
Supporting Documents
Related Meeting
Council - Friday 25 July 2025 10.00 am on July 25, 2025