Decision
Project funding - Roman Baths Shop Refurb
Decision Maker: Executive Director - Sustainable Communities
Outcome: Approved
Is Key Decision?: No
Is Callable In?: No
Date of Decision: June 20, 2025
Purpose: Phase one of the refit of the Roman Baths Shop is now complete with the space in use. There was a slightly higher than budgeted redecoration cost.
Content: To approve £4,064.19 from the Heritage Infrastructure Development budget, to fund a small overspend on this project.
Related Meeting
Planning Committee - Wednesday 27th August 2025 10.00 am on August 27, 2025