Decision

RESPONSIBLE ADVENTURE CHANGE REQUEST

Decision Maker:

Outcome:

Is Key Decision?: No

Is Callable In?: No

Date of Decision: July 11, 2025

Purpose:

Content: 1.     To agree the request for change for the Responsible Adventures project, making the following changes: a)    To approve the removal of the eBus element from the project scope b)    To approve the process of developing and delivering a business case c)    To confirm that the two remaining conditions imposed during approval of the Outline Business Case have been adequately met and that the project can proceed to submit business cases for funding approval in accordance with the step-by-step delivery proposal in the change request. d)    To request further detailed information on the proposed change request to replace the eBus element of the project with the development of a Forest Masterplan at Betws y Coed and that this will be submitted to the next Sub-Committee in October for consideration.