Alex Hearn

Council: Bristol

Committees: Full Council (Officer) Strategy and Resources Policy Committee (Officer) Public Health and Communities Policy Committee Homes and Housing Delivery Policy Committee (Officer) Environment and Sustainability Policy Committee (Officer) Economy and Skills Policy Committee (Officer) Transport and Connectivity Policy Committee (Officer) Cabinet Communities Scrutiny Commission Growth and Regeneration Scrutiny Commission

Activity Timeline

Meetings Attended Note this may include planned future meetings.

84 meetings · Page 1 of 17

Homes and Housing Delivery Policy Committee Officer

Homes and Housing Delivery Policy Committee - Friday, 19th December, 2025 10.00 am

December 19, 2025
Strategy and Resources Policy Committee Officer

Strategy and Resources Policy Committee - Monday, 15th December, 2025 2.00 pm

December 15, 2025
Full Council Officer

Full Council - Tuesday, 9th December, 2025 2.00 pm

December 09, 2025
Economy and Skills Policy Committee CANCELLED Officer

Economy and Skills Policy Committee - Monday, 8th December, 2025 2.00 pm

December 08, 2025
Strategy and Resources Policy Committee Officer

Strategy and Resources Policy Committee - Monday, 17th November, 2025 2.00 pm

November 17, 2025

Decisions from Meetings

312 decisions · Page 34 of 63

Response to Full Council Golden Motion Make Bristol the UK’s Most Accessible City

From: Transport & Connectivity Policy Committee - Thursday, 20th March, 2025 5.00 pm - March 20, 2025

To respond in full to the Golden Motion approved at Full Council on 8 October 2024 and to consider the ‘Bristol Climate and Nature Partnership’s Inclusive Transport Vision for Bristol’.

Recommendations Approved

City Centre – Bedminster Bridges Outline Business Case and Construction Delivery

From: Transport & Connectivity Policy Committee - Thursday, 20th March, 2025 5.00 pm - March 20, 2025

To seek approval to submit the Bedminster Bridges Outline Business Case (OBC) to the West of England Combined Authority (WECA) to secure funding to continue development of the project up to full business case (FBC) stage and subject to approval to take all steps required to accept and spend the funding, and to procure and award the necessary contracts for this project up to FBC (which may be over the key decision threshold), in-line with the procurement routes and maximum budget envelopes outlined in the report. To delegate authority to approve the subsequent FBC to the Executive Director for Growth and Regeneration in consultation with Chair of the Transport and Connectivity Committee. To seek approval to commence physical works after OBC approval in parallel to seeking FBC approval and therefore seek approval to accept and spend funding, procure and award contacts for the development and delivery of the Bedminster Bridges Project (part of the City Centre Scheme).

Recommendations Approved

Hackney Carriage Fare Review

From: Transport & Connectivity Policy Committee - Thursday, 20th March, 2025 5.00 pm - March 20, 2025

To seek approval for a revised table of fares for Hackney Carriage Vehicles.

Recommendations Approved

Pedestrian Priority at stand-alone push button crossings in Bristol

From: Transport & Connectivity Policy Committee - Thursday, 20th March, 2025 5.00 pm - March 20, 2025

To seek approval to the roll-out of Pre-Timed Max (PTM) on standalone pedestrian crossings across the city.

Recommendations Approved

City Centre Transport Corridor – Temple Way FBC

From: Transport & Connectivity Policy Committee - Thursday, 20th March, 2025 5.00 pm - March 20, 2025

To seek approval to submit the Full Business Case to the West of England Combined Authority (WECA) and subject to approval, to accept and spend the funding to deliver the City Centre Transport Corridor Temple Way

Recommendations Approved

Summary

Meetings Attended: 84

Average per Month: 3.7

Decisions Recorded: 312