Summary

...to note the forecast outturn position for Revenue, HRA, and DSG as at month 3, approve funding for the 2025 Pride Awards and the Together campaign, approve additional capital funding for Soho Theatre, approve funding for fit-out works on Unit C Soho Theatre, and approve funding for the Oracle stabilisation programme.

Full council record
Purpose

Cabinet is recommended to Note the forecast outturn
position for Revenue, Capital, HRA and DSG as at month
3.  
 

Content

Cabinet:
 

(1)          
noted the forecast outturn position for Revenue, HRA and DSG as at
month 3;
 
(2)          
approved £0.015 million funding from the budget strategy
reserve (BSR) to fund the 2025 Pride Awards and £0.145
million towards the together campaign from the BSR;
 
(3)          
approved £0.500m additional capital funding for Soho Theatre
due to extended timelines to complete works (September 2024 to
March 2025);
 
(4)          
approved an amount not exceeding £0.300m, to be funded from
capital contingency, for fit out works on Unit C Soho
Theatre.  This is to enable the unit to
be let on a commercial basis (i.e. ducting and electrical upgrade);
and
 
(5)          
approved £0.984 million to fund the Oracle stabilisation
programme, of which £0.894 million is to capital related to
be funded from the capital contingency and £0.089 million is
revenue expenditure to be funded from the corporate revenue
contingency budget.
 
Options &
Alternatives Considered
 
Much of this report is
concerned with provision of information, for which alternative
options is not a relevant consideration.
 

Related Meeting

Cabinet - Tuesday, 9th September, 2025 2.00 pm on September 9, 2025

Supporting Documents

Budget Monitoring - Month 3 Cabinet Report.pdf

Details

OutcomeFor Determination
Decision date9 Sep 2025