St Ann's Hill Balustrade project
Decision Maker:
Outcome: Recommendations Approved
Is Key Decision?: No
Is Callable In?: No
Date of Decision: September 10, 2025
Purpose:
Content: Resolved that – authority be granted to proceed with a grant application, and commence a procurement exercise, subject to approval of the potential funding gap, as identified in the report; and Recommendation to Corporate Management Committee as set out in the Part II report agreed Officer Action Officers (DW/CP) to provide a referral to Corporate Management Committee on 25 September 2025, and to include how long the replacement wall would likely last and how long the site would likely be closed off to the public
Related Meeting