Decision

HIF1 Didcot Science Bridge Contractor Appointment

Decision Maker: Delegated Decisions by Cabinet Member for Place, Environment and Climate Action

Outcome: Recommendations Approved

Is Key Decision?: Yes

Is Callable In?: Yes

Date of Decision: December 11, 2025

Purpose: Decision required whether to let the contract for the construction of the HIF1 Didcot Science Bridge scheme.

Content: The Cabinet Member is RECOMMENDED to:   a) Approve the award of a contract for the construction of Didcot Science Bridge Scheme under the HIF1 programme to the Preferred Bidder; and   b) Authorise the Director of Environment and Highways to finalise the contract terms and enter into a construction contract with the Preferred Bidder for the Didcot Science Bridge (DSB) scheme under the HIF1 programme.

Supporting Documents

CMDPECA11122025 - HIF1 Science Bridge Contractor.pdf