District Heating Transmission Pipeline - CORS/26/019

February 10, 2026 Finance and Resources Committee (Committee) Awaiting outcome View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...authorised the Chief Officer - Commercial and Procurement to commission external resources, initiate a tender for a design and build framework, issue a call-off order for detailed design to RIBA Stage 4 including network compatibility assessment, and request a fixed price for the construction of the district heating transmission pipeline.

Full council record
Content

(a)      Notes the proposed route
and estimated return on investment to construct, operate and
maintain the district heating transmission pipeline in Appendix 1,
Section 4 – Financial Case;
(b)      Authorises the Chief
Officer - Commercial and Procurement to commission the necessary
ancillary external resources to support the project delivery, to
undertake a procurement exercise to invite tenders for a design and
build framework contract, and, upon completion, to issue a call-off
order for the detailed design of the district heating transmission
pipeline to RIBA Stage 4 (to include a survey and assessment of the
existing Aberdeen Heat and Power City Centre and Seaton heat
network to ensure technical compatibility), and to request a fixed
price from the contractor for the construction of the transmission
pipeline.

Supporting Documents

District Heating Transmission Pipeline_Final Committee Report.pdf

Details

OutcomeFor Determination
Decision date10 Feb 2026