HofT&D/035/26-27 Gigabit Phase 3 - WAN Solution
September 29, 2026 Head of Technology & Design (Officer) Key decision Awaiting outcome View on council websiteFull council record
Decision
To migrate fibre networking across 22 council sites from current bespoke service arrangements to SD-WAN over CityFibre network using commercial ISP.
The total purchase value is £129,918.43 + VAT from KHIPU Networks Ltd for 3 years via SBS DWS2 framework direct award.
Reasons for the decision
Cost reduction in relations to current services and renewal of equipment and leased space. The decision is the most cost effective way to continue critical network services.
Alternative options considered
Continuing the current arrangement, however this would require an even more significant level of capital expenditure to renew equipment.
Details
| Reference | Call-ins0 |
| Outcome | For Determination |
| Decision date | 29 Sep 2026 |
| Effective from | 7 Oct 2026 |
| Lead officer | Simon Millier |
| Subject to call-in | Yes |