Primary Special School Development (Cab.07.10.2026/7)

October 7, 2026 Cabinet (Cabinet collective) Key decision Approved View on council website
Full council record

Purpose

Approval of the ongoing programme development for in borough Primary School special places.

Decision

RESOLVED That Cabinet:-

  1. Note the progress made since the October 2025 Cabinet decision, including the appointment of Waterton Academy Trust as the preferred strategic education partner, development of interim provision from September 2026 and completion of further feasibility, survey, design and cost planning work for The Mill.
  2. Approve the revised capital allocation of £7.37m for the refurbishment and development of The Mill to provide 40 specialist primary places, replacing the previously approved budget of £2.97m.
  3. Approve the revised delivery programme, recognising that interim provision will operate from Kings Oak during 2026/27 while the permanent provision at The Mill is progressed.
  4. Delegate authority to the Executive Director Children’s Services, Director of Finance and Director of Law, Democratic and Member Services, in consultation with the Cabinet Member for Children’s Services, to finalise the partnership, contractual, financial, procurement and delivery arrangements necessary to progress the scheme.

Related Meeting

Cabinet - Wednesday 7 October 2026 10.00 am on October 7, 2026

Supporting Documents

Primary Special School Development Report.pdf
Appendix A - Financial Implications.pdf
Appendix B - IAT Primary Special School Development.pdf

Details

ReferenceCall-ins0
OutcomeRecommendations Approved
Decision date7 Oct 2026
Effective from14 Oct 2026
Expected date7 Oct 2026
Originally due7 Oct 2026
Subject to call-inYes