Works to Swallow Street Buildings
February 6, 2025 Executive Director - Sustainable Communities (Officer) Approved View on council websiteFull council record
Purpose
This project completes work to the historic
Victoria Spa buildings which was not undertaken as part of the
Archway Project in 2020. It will provide staff facilities, a
changing room and storage facility for the Operations Team and
costumed interpretors who work at the Roman Baths and across the
Heritage Services Estate.
Currently these staff have inadequate welfare facilities and recent
Radon testing has highlighted a statutory requirement to relocate
staff from the areas previously used. The project will address this
compliance issue.
Decision
To fully approve capital amounting to 125k
from the provisional capital programme item Heritage Infrastructure
Development of £550k.
Details
| Outcome | Approved |
| Decision date | 6 Feb 2025 |