Case for Change

September 10, 2026 Cabinet (Cabinet collective) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Cabinet of Bath and North East Somerset Council decided on 10 September 2026 to confirm its support for the case for change and to agree the continuation of the transformation programme. A draft transformation plan will be presented to the Corporate PDS panel for discussion before adoption by Cabinet alongside the MTFS in November.

Full council record

Purpose

The council faces a challenging financial position as a result of rising demand and the government's Fair Funding Review. This paper describes how the council intends to change the way it works to become more resident-focused and efficient.

Decision

  1. To confirm its support of the case for change.
  2. To agree that the council should continue to develop the transformation programme as a key strand of the MTFS.
  3. To note that a draft transformation plan that responds to this paper will go to Corporate PDS panel in September for discussion ahead of adoption at Cabinet alongside the MTFS in November.

Reasons for the decision

B&NES has largely been able to avoid significant cuts to frontline services through a combination of strong financial management, increasing our income and making incremental changes to the way we work. This will not be enough to tackle the challenge we face over the next three years. The council remains ambitious for the local economy and our communities, but we can only deliver those ambitions if we are prepared to work differently.

Alternative options considered

The transformation programme is being designed in partnership with a wide range of officers and stakeholders. Many different options have been considered and we will select the ones we believe most likely to deliver benefits in line with this plan.

We considered bringing in an external transformation partner to deliver this work with us. This was rejected on grounds of cost and control, and because it was felt that working with a partner would reduce the scope for developing the right skills and culture among our in-house team. External support remains an option for specific elements of the programme.

We considered not having a transformation programme at all. This was rejected

because it would force us into deeper cuts to frontline services than might otherwise be necessary.

Related Meeting

Cabinet - Thursday, 10 September 2026 - 6.30 pm on September 10, 2026

Supporting Documents

E3733 - Decision Case for Change.pdf
Case for Change.pdf

Details

ReferenceCall-ins0
OutcomeApproved
Decision date10 Sep 2026
Effective from19 Sep 2026
Expected date10 Nov 2026
Originally due10 Sep 2026
Lead officerSimon Parker
Subject to call-inYes