Transfer of St Joseph's building and funds to open a SEMH special school

October 14, 2026 Executive (Other) Approved View on council website
Full council record

Decision

Description of Decision

(1)  That the transfer of the St Joseph’s Lower School building to Meridian Trust on a 125-year lease, subject to

  Secretary of State approval of Meridian Trust, be approved.

(2)  That it be agreed to release a capital grant of £2.5m for the works, paid in stages against evidenced expenditure

  and delivery milestones under grant terms and conditions, together with pre-opening costs to Meridian Trust to

  open a Social, Emotional, Mental Health (SEMH) Special School.

(3)  That it be noted that the Council’s total capital commitment to the scheme is £4.3m, funded entirely from High

  Needs Capital Allocation, and that no further Council funding is committed by this decision. Any further funding

  would require a separate approval through the Council’s normal governance.

(4)  That authority be delegated to the Executive Director for Children, Education and Families (DCS), in consultation

   with the Section 151 Officer and the Monitoring Officer, to finalise the lease and the grant terms and conditions in

  line with the principles set out in this report.

Reason for Decision

To ensure local children are able to attend provisions closer to home, reduce home to school transport expenditure, contribute towards reduction to High Needs deficit, and lead to reductions in exclusions across Bedford Borough, directly supporting the Council’s statutory SEND duties and the local SEND Reform Plan.

Related Meeting

Executive - Wednesday, 14th October, 2026 2.30 pm on October 14, 2026

Supporting Documents

Item 07-Transfer of St Josephs.pdf

Details

OutcomeRecommendations Approved
Decision date14 Oct 2026