Blackpool Multiversity Campus - Main Contractor: Pre-Enabling Works Contract

December 24, 2024 Director of Communications and Regeneration (Officer) Approved View on council website
Full council record

Purpose

To approve the appointment of
Morgan Sindall Construction & Infrastructure Limited, via a
pre-enabling works contract, to continue as the main contractor for
the second stage tender process for the Multiversity
Campus

Decision

To
approve the appointment of Morgan Sindall Construction &
Infrastructure Limited (Morgan Sindall), via a pre-enabling works
contract, as the main contractor for the pre-enabling works in
advance of the second stage tender process for the Multiversity
Campus being completed.
 

To
authorise the Head of Legal Services to enter into any legal
contracts and or documentation required to implement this
decision.
 

 

Supporting Documents

ONKD - Multiversity Campus Main Contractor - PEWks rev A.pdf

Details

OutcomeRecommendations Approved
Decision date24 Dec 2024