New Dwellings - Alder Close, Shirebrook

January 27, 2025 Approved View on council website
Full council record

Decision

RESOLVED that 1) subject to planning approval, Executive
approves the capital expenditure budget as outlined within the
report to deliver the Alder Close affordable housing building
scheme in the amount of £2,035,877 (less £670,000)
– Scenario 1, Table 1,
 
2) subject to
planning approval, a report be submitted to Council to update the
schemes included in the Bolsover Homes pipeline funding envelope of
£36.2m for the Alder Close, Shirebrook scheme which was
currently not included.
 
3) subject to
planning approval, Executive agrees that the Council enters into
contract with Dragonfly Development Limited for the development of
Alder Close as outlined in the report, subject to Council approval
for inclusion in Bolsover Homes pipeline funding.
 

Related Meeting

Executive - Monday, 27th January, 2025 10.00 am on January 27, 2025

Supporting Documents

1. Report to Executive for Jan 25 - Alder Close.pdf
2. Appendix 1 report to executive Site Layout Alder Close.pdf

Details

OutcomeApproved
Decision date27 Jan 2025
Subject to call-inYes