Moulsecoomb Hub and Housing Project
March 13, 2024 Housing & New Homes Committee, Strategy, Finance & City Regeneration Committee (Committee) Awaiting outcome View on council websiteFull council record
Purpose
An update on the Moulsecoomb project seeking approval for a way forward
Decision
RESOLVED:
That Housing and New Homes Committee recommends to Strategy, Finance and City Regeneration Committee to:
- 1 Agree to begin a procurement exercise for the redevelopment of this site, including early market engagement.
- 2 Delegate authority to the Executive Director of Environment, Economy & Culture and the Executive Director Housing, Neighbourhoods & Communities to procure the contractors and then once a budget has been agreed at a subsequent committee meeting, to then enter in to relevant contracts.
- 3 Note that the demolition of some of the existing buildings is due to commence in March 2024.
Supporting Documents
Details
| Decision date | 13 Mar 2024 |