Moulsecoomb Hub and Housing Project

March 13, 2024 Housing & New Homes Committee, Strategy, Finance & City Regeneration Committee (Committee) Awaiting outcome View on council website
Full council record

Purpose

An update on the Moulsecoomb project seeking approval for a way forward

Decision

            RESOLVED:

That Housing and New Homes Committee recommends to Strategy, Finance and City Regeneration Committee to:

  1. 1      Agree to begin a procurement exercise for the redevelopment of this site, including early market engagement.
  2. 2      Delegate authority to the Executive Director of Environment, Economy & Culture and the Executive Director Housing, Neighbourhoods & Communities to procure the contractors and then once a budget has been agreed at a subsequent committee meeting, to then enter in to relevant contracts.
  3. 3      Note that the demolition of some of the existing buildings is due to commence in March 2024.

Supporting Documents

Moulsecoomb Hub and Housing Project.pdf

Details

Decision date13 Mar 2024