Summary

...to address insufficient contractor interest in major works projects over £300,000, the committee delegated authority to the Executive Director Housing, Neighbourhoods & Communities to procure a new framework agreement or use alternative procurement routes.

Full council record

Purpose

This report seeks approval for the dissolution of the existing Housing major capital works framework arrangement for Lot 2, works over £300,000, due to our being unable to secure sufficient tenders from the contractors currently on the framework. The report recommends replacement of this element of the framework with the procurement of a compliant alternative framework and /or formation of a suitable list of approved contractors for each project to ensure that we receive sufficient tender bids for assurance of value for money and cost comparison.

Decision

RESOLVED:

  1. 1      That Committee delegates authority to the Executive Director Housing, Neighbourhoods & Communities to procure a Framework Agreement for major works over £300,000 and to enter into call-off contracts for works under that Framework Agreement.
  2. 2      That Committee grants delegated authority to the Executive Director Housing, Neighbourhoods & Communities to procure and award contracts for major works over £300,000 using other routes to market where the use of a Framework Agreement is not available or appropriate.

Supporting Documents

Housing Major Capital Works Framework review of procurement options.pdf

Details

OutcomeFor Determination
Decision date20 Sep 2023