A259 Active Travel Improvement Scheme Fourth Avenue - Wharf Road
June 21, 2023 Transport & Sustainability Committee (Committee) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to meet the administration's requirements, the committee agreed to redesign the A259 Fourth Avenue to Wharf Road active travel scheme, acknowledging the need for significant additional funding and delegating authority to terminate the current contract.
Full council record
Purpose
This is a special report following the
administrations requirements for the scheme. The report makes
recommendations to enable officers to meet the requirements of the
administration.
Content
1)
That the Committee agrees to redesign the A259
Fourth Avenue to Wharf Road scheme.
2)
That the Committee notes that significant
additional funding will be required to redesign and deliver the
final scheme. The final scheme design and funding requirements will
be subject to a further report to this committee, including funding
sources such as other external grant or reallocation of the
Councils Programme.
3)
That Committee delegates authority to the
Executive Director, Economy, Environment & Culture to take all
steps necessary to terminate the current call-off Contract for the
A259 Fourth Avenue to Wharf Road Active Travel Scheme and notes the
financial implications of both the stand-down charges and
termination fees as detailed in section 7 of this
report.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 21 Jun 2023 |