Frome Gateway Regeneration Framework

February 6, 2024 Cabinet (Cabinet collective) Key decision Approved View on council website
Full council record
Purpose

1. To seek
approval of the Frome Gateway Regeneration Framework.
2. To seek approval for the acquisition of land in relation to the
Bedminster Green Framework Area.
3. To note the proposals in relation to two Council owned sites in
the Regeneration Framework area at Universal House and the
Wellington Road depot site.

Content

That Cabinet:
 
Frome Gateway

1.     
Approved the Frome Gateway Regeneration Framework and note that it
will be a material planning consideration in the determination of
planning applications.

2.     
Authorised the Executive Director for Growth and Regeneration in
consultation with the Mayor to secure
the freeholder requirements set out in this report through lease
re-gearing negotiation in the Frome Gateway area and to note the
costs of these requirements will be considered when determining
best value.

3.     
Authorised the Executive Director for Growth and Regeneration in
consultation with the Mayor to take all
steps required to deliver a last-mile logistics hub on the
Universal House site and an energy centre with larger family
accommodation on the Wellington Road Depo Site as set out in this
report.

4.     
Authorised the Executive Director of Growth and Regeneration, in
consultation with the Section 151 Officer and Mayor, to explore and
to submit funding bids (which may be over the key decision
threshold) to enable the redevelopment of Frome Gateway, noting
that the acceptance and spend of any funding award over the key
decision threshold will be subject to further approval in
accordance with the decision pathway.

5.     
Authorised the Executive Director of Growth and Regeneration, in
consultation with the Section 151 Officer and Mayor, to explore and
to submit funding bids (which may be over the key decision
threshold) to enable development of a Community Land Trust or
similar appropriate vehicle to run and manage community and
cultural spaces in Frome Gateway, noting that the acceptance and
spend of any funding award over the key decision threshold will be
subject to further approval in accordance with the decision
pathway.

6.     
To authorised the Executive Director of
Growth and Regeneration, to implement a local lettings policy in
the Frome Gateway Regeneration area.

7.     
Noted the consultation report at Appendix B.
 
Bedminster Green

8.     
Authorised the Executive Director in consultation with the Cabinet
Member for Growth and Regeneration to take all steps required to
acquire the land as outlined in this report.

Supporting Documents

Appendix A 1 - Frome Gateway Regeneration Area Boundary.pdf
Appendix A 3 - Universal House Site Plan.pdf
Appendix E - Frome Gateway EQIA - for Cabinet report_FINAL signed-off.pdf
Appendix A 4 - Wellington Road Depo Site Plan.pdf
Appendix A 2 - Frome Gateway_Spatial Regeneration Framework_FINAL JAN 24_reduced.pdf
Appendix A 5 -land to the north of Bedminster Green Plot 3.pdf
Appendix Biii - Frome Gateway Statement of Community Involvement.pdf
Appendix Bi - Frome Gateway Regeneration Framework Formal Consultation Report.pdf
Appendix Bii - Frome Gateway Framework Consultation Response.pdf
Appendix D - Risk Register - Frome Gateway Framework.pdf
Frome Gateway Framework Decision Pathway Report Feb 2024.pdf
Appendix F - Environmental Impact Assessment - Frome Gateway SRF.pdf

Details

OutcomeRecommendations Approved
Decision date6 Feb 2024
Subject to call-inYes