Underfall Yard – Initial Capital Works & Professional Fees
September 14, 2023 Executive Director: Growth and Regeneration (Officer) Approved View on council websiteFull council record
Purpose
The decision enables Underfall Yard Trust
(UYT) to make the site safe, mitigate the risk of further
deterioration of the condition of the building and provide the best
possible access to public realm for Bristol citizens using
insurance funds awarded to the Council by Zurich for the
reinstatement of the Underfall Yard. The decision is to carry out
of initial capital works to make the area safe and clear, carry out
repairs and reopen the Harbourside walkway. It includes
professional fees for initial design work for the full
rebuild.
Content
Approval to take all steps required for the
Underfall Yard Trust (UYT) to carry out initial capital works to
Underfall Yard.
Details
| Outcome | Recommendations Approved |
| Decision date | 14 Sep 2023 |