City Centre Transport Corridor – Temple Way FBC

March 20, 2025 Transport & Connectivity Policy Committee (Committee) Key decision Approved View on council website
Full council record
Purpose

To seek approval to submit the Full Business
Case to the West of England Combined Authority (WECA) and subject
to approval, to accept and spend the funding to deliver the City
Centre Transport Corridor Temple Way

Content

That the Committee
for Transport and Connectivity:

 
1.
    Approved submission of the
Temple Way FBC for approval at WECA Committee or WECA
Directors.

 
2.
    Authorised the Executive
Director for Growth and Regeneration in consultation with Chair of
the Transport and Connectivity Committee to take all steps required
to procure and award the necessary contracts for this project
(which may be over the key decision threshold), in line with the
procurement routes and maximum budget envelopes outlined in this
report, should the FBC be approved by the WECA Committee.
 

Supporting Documents

Appendix C - Environmental Impact Assessment - Temple Way.pdf
Appendix A - App H1 Temple Way General Arrangement Drawings.pdf
Committee Report - Temple Way.pdf
Committee Report - Temple Way - updated link.pdf
Appendix B - Equality Impact Assessment - Temple Way.pdf
Appendix H - Temple Way FBC - REDACTED.pdf
Appendix H2A Temple Way_AMAT v0.3_HighCase.pdf
Appendix H2B Temple Way_AMAT v0.3_LowCase.pdf
Appendix H2E Temple Way_SSAT_LowCase.pdf
Appendix H3 - AST.pdf
Appendix H4 - Strategic Transport Modelling of Bristol City Centre Schemes.pdf
Appendix H5- TempleWay LinSig Summary.pdf
Appendix H6 - Project Schedule.pdf
Appendix H7 - Risk Register.pdf
Appendix H8 - Data Collection.pdf
Appendix H2C Temple Way_SSAT_HighCase.pdf
Appendix H2D Temple Way_SSAT_CentralCase.pdf

Details

OutcomeRecommendations Approved
Decision date20 Mar 2025
Subject to call-inYes