Second additional costs for Jacobs to complete role as NEC PM team for Harbour Walkway
April 16, 2025 Director: Economy of Place (Other) Approved View on council websiteFull council record
Purpose
Jacobs, via Perfect Circle, have provided the
NEC Project Management and Supervision team for the Harbour Walkway
project since 2018. Because of the delays caused by the recent
harbour bank failure and other delays encountered as part of the
construction, further funding is required to complete their role
until the end of the project construction and throughout the
12-month defect period, as noted in the 6 February 2025 Committee
report.
Content
To accept Perfect Circle compensation event
3821-002 CE04 and permit an order to be raised for
£263,283.37.
It will also be requested that Jacobs attend the project’s
Lessons Learnt process at no further cost.
Details
| Outcome | Recommendations Approved |
| Decision date | 16 Apr 2025 |