A38S M1 Metrobus extension and active travel corridor

July 10, 2025 Transport & Connectivity Policy Committee (Committee) Key decision Approved View on council website
Full council record
Purpose

To seek approval for the submission of a Low
Risk Transport Scheme (LRTS) Full Business Case (FBC) to the West
of England Mayoral Combined Authority (MCA) for City Regional
Sustainable Transport Settlement (CRSTS) funding and subject to
approval, to accept and invest the funding to deliver the A38S M1
Metrobus Extension and Active Travel Corridor.

Content

That the Committee for Transport and Connectivity

1.       
Approved the submission of the LRTS FBC for the A38S M1 Metrobus
Extension and Active Travel Corridor CRSTS Project to the MCA
Contractual:

2.       
Authorised the Executive Director of Growth and Regeneration in
consultation with Chair of the Transport and Connectivity Committee
and Director Finance, subject of approval of the Full Business Case
by the MCA to:
a. Take all steps
required to accept and invest the CRSTS funding amount as set out
in the report and appendices,
b. Procure all contracts
(goods, services and works and including any over £500K)
necessary to deliver the project,
c. Extend the value of
the existing Highways and Associated Works framework if there is
insufficient spend remaining to cover the project which may be
procured before its expiry on 30th September 2025,
d. Award contracts and
invest the funding to deliver the works as set out in the LRTS FBC
up to the maximum budget envelope outlined in the report.

 

Notes:

3.        Noted
the consultation report at Appendix C of Appendix H (LRTS FBC).

Supporting Documents

01 - Committee Report A38S m1 metrobus extension and active travel corridor.pdf
Appendix A1 - BD16772 - m1 route extension - hartcliffe.pdf
Appendix A6 - A38 S Metrobus Extension - General Arrangement 3.pdf
Appendix A7 - A38 S Metrobus Extension_Bus Stops - General Arrangement.pdf
Appendix B - Equality Impact Assessment -A38S M1 Metrobus Extension and Active Travel Corridor signe.pdf
Appendix C - Environmental Impact Assessment - A38S M1 Metrobus Extension and Active Travel Corridor.pdf
Appendix D - PR_001- P0011.2 - A38 South M1 Metrobus Extension RAID log April 2025.pdf
Appendix H - A38S m1 Metrobus Extension FBC_FINAL - REDACTED.pdf
Appendix A2 - BD16772 - cycle lane improvements - M1 Hartcliffe.pdf
Appendix A3 - Upcoming Development Applications Hengrove.pdf
Appendix A4 - A38 S Metrobus Extension - General Arrangement 1.pdf
Appendix A5 - A38 S Metrobus Extension - General Arrangement 2.pdf

Details

OutcomeRecommendations Approved
Decision date10 Jul 2025
Subject to call-inYes