Enabling Works and Pre Construction Services for Elmfield Secondary school at Badock’s Wood Academy site.
September 22, 2025 Executive Director: Children & Education (DCS) (Officer) Key decision Approved View on council websiteFull council record
Purpose
The project is part of the Education Capital
programme. Approval was given at the Children
Content
To progress with the minor works comprising
enabling work and pre-construction services and detailed design to
support the relocation of Elmfield Secondary school to the current
Badock’s Wood Academy school site.
Alternative options considered
Following an intensive search, a positive
opportunity was identified to utilise one of two buildings at
Badock’s Wood Academy (Primary). This is currently the only
option that is available to support the relocation of Elmfield
Secondary to an appropriate provision within the parameters.
Details
| Outcome | Recommendations Approved |
| Decision date | 22 Sep 2025 |