Concorde Way (Dovercourt Road) cycling scheme Full Business Case

October 22, 2026 Transport & Connectivity Policy Committee (Committee) Key decision In call-in window View on council website
Full council record

Purpose

To seek approval to submit the Full Business Case (FBC) to the West of England Mayoral Combined Authority (MCA) for Concorde Way (Dovercourt Road) cycling scheme.

Decision

That the Committee for Transport and Connectivity

  1. 1.      Approved the submission of the Full Business Case (FBC) to the West of England Mayoral Combined Authority (MCA).

Contractual:

  1. 1.      Authorised the Executive Director of Growth and Regeneration in consultation with the Chair of the Transport and Connectivity Committee to accept the funding offered on MCA’s approval of the FBC and award the relevant construction contract(s), in-line with the procurement routes and maximum budget envelopes outlined in this report.
  2. 2.      Authorised the Executive Director of Growth and Regeneration to approve extensions or variations specifically provided for within the awarded contract, within the confirmed maximum scheme budget and external funding envelope, with no additional unfunded commitment to the Council.

Supporting Documents

Appendix A1 - General Arrangement 1 of 6.pdf
Appendix A2 - General Arrangement 2 of 6.pdf
Appendix A3 - General Arrangement 3 of 6.pdf
Appendix A4 - General Arrangement 4 of 6.pdf
Appendix A5 - General Arrangement 5 of 6.pdf
01. Committee Report - Concorde Way v4.pdf
Appendix B - Equality Impact Assessment - Concorde Way.pdf
Appendix C - Environmental Impact Assessment - Concorde Way.pdf
Appendix A6 - General Arrangement 6 of 6.pdf
Appendix H - Draft Concorde Way ATSA FBC.pdf

Details

ReferenceCall-ins0
OutcomeRecommendations Approved (subject to call-in)
Decision date22 Oct 2026
Expected date22 Oct 2026
Originally due22 Oct 2026
Lead officerAdam Crowther
Subject to call-inYes