Canford Crematorium – Replacement of cremators

September 11, 2026 Public Health and Communities Policy Committee (Committee) Key decision Approved View on council website
Full council record

Purpose

To seek approval to progress the Canford Crematorium project and allocate funding for the replacement of gas cremators with electric technology.

Decision

The Committee RESOLVED (unanimously) to

  1. Approve the allocation of £8.649m of capital funding for the replacement of gas cremators with electric cremators at Canford Crematorium as set out in this report.
  2. Authorise the Executive Director of Growth & Regeneration in consultation with Chair of the Public Health and Communities Committee and Director Finance to continue the design and delivery of the project within the approved budget envelope, subject to PAC Stage 2 approval.
  3. Note that progression of the project will be subject to the council’s internal decision pathway process.
  4. Authorise the Executive Director of Growth & Regeneration in consultation with the Chair of the Public Health and Communities Committee and Director Finance, to take all steps required in accordance with the council’s internal decision pathway process to procure and award the contract to deliver the scheme in line with the maximum budget envelopes outlined in this report.
  5. Authorise the Executive Director of Growth & Regeneration in consultation with the Chair of the Public Health and Communities Committee and Director Finance, to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.

Supporting Documents

7.1 Canford Crematorium - Committee Report.pdf
7.2.1 Appendix A - Proposed Visuals - Canford Crematorium.pdf
7.2.2 Appendix A1 - Peace Garden Landscape Design - Canford Crematorium.pdf
7.3 Appendix B - Canford Stage 1 - Equality Impact Assessment.pdf
7.4 Appendix C - Canford Crematorium - Environmental Impact Assessment.pdf

Details

OutcomeRecommendations approved
Decision date11 Sep 2026
Effective from19 Sep 2026
Expected date11 Sep 2026
Originally due11 Sep 2026
Lead officerRichard Fletcher
Subject to call-inYes