Elmfield Secondary School for Deaf Children – relocation to E-Act Badock’s Wood Primary school site Further Contract Variation
November 10, 2026 Executive Director: Children & Education (DCS) (Officer) Approved View on council websiteFull council record
Purpose
This project is part of the Education Capital programme. The project is to relocate Elmfield Secondary school to the current site of E-Act Badock’s Wood Primary school on Doncaster Road. The existing school site will be broadly divided equally between both schools with construction works to refurbish one building for E-Act Badock’s Wood Primary school and the other building refurbished and repurposed for Elmfield Secondary school.
The project budget approved on the 8th May 2025 Children and Young People Committee included contingency allowances for the management of the works contract and authorised the Executive Director for Children and Education in consultation with Chair of the Children and Young People Committee to approve the final business case for the relocation of Elmfield Secondary School for Deaf Children from Fairfield High to the Oak Block at Badock’s Wood Academy (Primary), and subject to this approval, take all steps required to spend the funding, including to procure and award contracts (which may be over the key decision threshold) for the design and construction works to support the delivery of Elmfield Secondary school, in-line with the procurement routes and maximum budget envelopes outlined in the committee report.
An additional £262,994 of funding, both from E-Act and the project’s contingency budget, was identified in an Officer Decision Notice of 28th September 2026 for the instruction of additional works under the associated JCT Construction Contract. Further utilisation of the project contingency funding is required to support the ongoing design development and associated construction works, plus works to address building related matters.
Decision
Approval to instruct additional variations to the Elmfield Secondary JCT Construction Contract funded by £418,223 from the project’s contingency budget.
Alternative options considered
Do Nothing was rejected as:
- The developed design and associated construction works are essential to provide the required specialist secondary teaching spaces.
- Building matters need to be addressed to ensure the completed refurbishment meets current standards.
Details
| Outcome | Recommendations Approved |
| Decision date | 10 Nov 2026 |