Education Capital Programme: SEND Wave 2 - Refurbishment of the Stable Block at North Star 82

October 29, 2024 Executive Director: Children & Education (DCS) (Officer) Key decision Approved View on council website
Full council record
Purpose

The project is part of the SEND Wave 2
Education Capital programme. The programme originally received
Cabinet approval on 6th September 2022 with costs re-baselined at
Cabinet in September 2023 where delegated authority was given to
Executive Director Children and Education to use basic need, High
Needs grant and schools Condition allowance to create additional
SEND pupil places across Bristol including the letting of contracts
in excess of £1 million. The Children

Content

To award the contract after a competitive
tender for comprehensive refurbishment of the Stable Block at North
Star 82 to create a re-modelled SEND facility for 16 existing
pupils, plus create space for a further expansion to include 6 more
places.

Details

OutcomeRecommendations Approved
Decision date29 Oct 2024