PROCUREMENT STRATEGY FOR LEISURE CENTRE MAJOR WORKS PROGRAMME

August 9, 2023 Executive (Other) Awaiting outcome View on council website
Full council record
Purpose

Following the 2022 Operational Property Review
and the RRH PDS Update report for Leisure Centres on June 15th
2023, this report seeks members' decision on the procurement
strategy for the main works contractor subject to approval of the
works programme later this year.

Content

1. 
The intent to seek formal decision by October 2023
on proceeding with the Walnuts and West Wickham Leisure Centre
project, including scope of works and agreed budget be
noted.
 
2. 
The in-principle procurement strategy set out in
Option 1 (paragraph 3.10 of the report) for the delivery of the
Walnuts and West Wickham Leisure Centre project by utilising a
compliant framework to appoint a suitable delivery partner to
deliver the project, including required works be
approved.
 
3. 
It be noted that any formal award of contract
arising from the in-principle procurement strategy will still be
subject to Executive decision and will not proceed except
alongside, or subsequent to, the primary decision to proceed with
the project as per (1) above.

Supporting Documents

Procurement Strategy for Leisure Centre Major Works Programme 07082023 Renewal Recreation and Ho.pdf

Details

OutcomeFor Determination
Decision date9 Aug 2023