WATERBODY MANAGEMENT: KELSEY PARK LAKE

July 5, 2023 Executive (Other) Key decision Deleted View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Bromley Executive decided on 05/07/2023 to approve variations to idverde's contract for survey work and desilting, proceed with procurement for a works contractor, and create a Project Manager post. Authority was delegated to the Director of Environment & Public Protection to award the works contract up to the remaining capital programme value.

Full council record

Decision

  1. A variation to idverde’s contract b agreed at a one-off value of £63k to undertake the survey work identified at paragraph 3.10 of the report and prepare the technical specifications for the tender of a works contractor.
  2. It be agreed to proceed to procurement for a works contractor to deliver the project in accordance with the procurement strategy set out in paragraphs 3.21 – 3.24 of the report.
  3. Authority be delegated to the Director of Environment & Public Protection, in consultation with the Portfolio Holder for Sustainability, Green Services and Open Spaces, to award the works contract to the successful tenderer up to the value remaining in the capital programme for the Kelsey Lakes.
  4. A 15-month fixed term Project Manager post be created to deliver the project using the capital programme funding for Kelsey Lakes at an estimated cost of £80k as set out in paragraph 3.27 of the report.
  5. A one-off variation to idverde’s contract of £17.5k for 2023/24 be approved to fund the desilting project at Croydon Canal identified at paragraph 3.29 of the report.

Supporting Documents

Kelsey Park Lakes 29062023 Environment and Community Services Policy Development and Scrutiny Com.pdf

Details

OutcomeDeleted
Decision date5 Jul 2023
Expected date5 Jul 2023
Originally due5 Jul 2023
Lead officerDavid Braybrook