CRM REPLACEMENT CAPITAL PROJECT - CRM & WEBSITE REDESIGN CLOSURE REPORT AND WEBSITE PHASE 2 OPTIONS

May 22, 2024 Executive (Other) Key decision Awaiting outcome View on council website
Full council record
Content

That
1. 
Under the CRM capital programme, the completion of the software
implementation and website redesign upgrade project of a value of
£491k leaving a remaining value
of £270k allocated to this
programme be noted.
2. 
It be agreed that the £270k
underspend be returned to the capital programme.
 