Betts Park Stabilisation Post Completion Review Report

September 13, 2024 Portfolio Holder for Environment (Cabinet member) Awaiting outcome View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to endorse the Betts Park Canal Stabilisation Scheme's post-completion review, remove the scheme from the Capital Programme, and note the removal of the £8,780 unspent balance from the Capital Programme.

Full council record
Content

The Environment Portfolio Holder noted that
the unspent balance of £8,780 had been removed from the
Capital Programme.
 
The Portfolio Holder endorsed the findings of
the post completion review for the Betts Park Canal Stabilisation
Scheme as outlined in the report.
 
The Portfolio Holder agreed that the scheme
could now be removed from the Capital Programme.

Reasons for the decision

As part of the Capital Programme Procedures it
was a requirement that capital schemes should be formally reviewed
following their completion and that the outcome of the review be
brought to the Portfolio Holder for endorsement.

Supporting Documents

Betts Park Stabilisation Post Completion Review Report 04092024 Environment and Community Service.pdf

Details

OutcomeFor Determination
Decision date13 Sep 2024