Cygnet Bridge (Change request) - KD2026/061

August 24, 2026 Chief Executive (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Chief Executive decided to approve recommendations on 24/08/2026. The decision extended the construction completion date for Cygnet Bridge and reprofiled £407,000 to 2027/28.

Full council record

Purpose

This change control seeks to update the construction completion date. The Cygnet Bridge started preliminary construction work on 11 May 2026 and is due to complete on 31 March 2027.The delivery target date set out in the previous change control (Jan 2025) set out that construction would be completed by Spring/Summer 2026.

Supporting Documents

ODN044-2026- Cygnet Bridge.pdf

Details

OutcomeRecommendations Approved
Decision date24 Aug 2026
Expected date23 Sep 2026
Originally due23 Sep 2026
Lead officerDomenico Cirillo