Whittlesea Station - ODN034-2026

July 17, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved a change request and a three-month extension to the project timeline for Whittlesea Station on 17/07/2026. This decision was made to accommodate challenges in obtaining critical data for the economic case. A variation to the existing GFA will be needed to reflect the revised timeline.

Full council record

Purpose

To approve the Change Request and approve that the project timeline is extended by three months.

Supporting Documents

ODN034-2026 - Whittlesea Station.pdf

Details

OutcomeRecommendations Approved
Decision date17 Jul 2026