Procurement Strategy for the Construction of New Depot Facilities at Freight Lane to Replace Existing Depot Facilities at Cedar Way
April 2, 2025 Director of Development (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve the procurement strategy for constructing new depot facilities at Freight Lane to replace those at Cedar Way, including a 40%/60% price/quality split and a three-month construction period.
Full council record
Purpose
This report outlines the strategy for the
procurement of a design and build contract for the relocation of
three Council service depots currently operating on the Cedar Way
industrial estate by construction of new depot facilities at two
sites on Freight Lane.
Approval is sought to issue an invitation to
tender to five contractors who are all believed to be capable of
delivering a project of the nature detailed in this
report.
Content
THAT the procurement strategy for the
construction of new depot facilities at Freight Lane, which
includes a price/quality split of 40%/60% and a three-month
construction period, for an estimated contract price specified in
Part II of this report.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 2 Apr 2025 |