November 4, 2025
Executive Director Investment, Place and Opportunity
(Officer)
Approved
View on council website
This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...the 18-week extension of time and additional works outlined in Batches 2 and 3 of the Talacre Community Sports Centre Remodelling Project contract with Corley Wooley Hospitality Limited were approved, while the additional works in Batch 4 were approved subject to funding being secured by the Leisure Service.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 4 Nov 2025 |