Summary

...to proceed with the legal process for permanently closing land at The Network Building and Whitfield Street, including public consultation and potential public inquiry.

Full council record
Purpose

This report requests the Director of Environment &
Sustainability to approve the processing of a stopping up order
(permanant road closure).
 

Content

THAT the Director of Environment &
Sustainability:

·       
Note the report and the highway authority’s
comments.

·       
Approve the advertising of the draft stopping up order for
public consultation to stop up all the land shown on the plan in
Appendix 1.

·       
Approve the order to be made and final advertisement should
no objections be received, or all objections being
withdrawn.

·       
Agrees that if objections are received which are not
withdrawn, the Mayor of London should be notified so a decision on
whether to hold a public inquiry can be made, as required by
legislation, should the applicant wish to proceed with the stopping
up order.

·       
Agrees that if a public inquiry is required by the Mayor of
London, it can be arranged and undertaken.

·       
Agrees that if the Mayor of London allows for the order to be
made without a public inquiry, the order can be made.
 

Supporting Documents

Report - Stopping Up of land The Network Building 95-100 Tottenham Court Road and 76-80 Whitfield S.pdf
Appendix 1 - Detailed plan showing land to be stopped up.pdf

Details

OutcomeRecommendations Approved
Decision date26 Jan 2024