Procurement Strategy for the Supply and Installation of Solar PV (photovoltaic system) at Henderson Court (Sheltered Blocks)

December 20, 2023 Director of Property Management (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve the procurement strategy for the £450,000 supply and installation of a solar PV system at Henderson Court via a closed tender process, and to proceed to the contract award stage.

Full council record
Purpose

This report outlines the procurement strategy for supply
and installation of a retrofit solar photovoltaic system (solar PV)
which will generate onsite renewable electricity at Henderson
Court.
 
The estimated contract value is £450,000 over an
estimated period of 6 months weeks, planned start March
2024.
 
The works are to be procured via a closed tender process
using a Joint Contracts Tribunal (JCT) Minor Works 2016 with
Contractors Design form of contract with Camden
amendments.
 

Content

THAT the Director of Property Management:
 

Approves the procurement strategy as set out in this
report for an estimated value of £450,000 including the use
of a closed tender process, with an evaluation criteria of 60%
price and 40% quality.

 
2.   
Approves that the project proceeds to the contract award
stage with the recommendation for contract award.
 

Supporting Documents

Procurement Strategy for the Supply and Installation of Solar PV photovoltaic system at Henderson.pdf

Details

OutcomeRecommendations Approved
Decision date20 Dec 2023