Subsurface Technology Electric Pathways (STEP) Electric Vehicle Charge Points Trial

December 19, 2023 Cabinet Member for Planning and a Sustainable Camden (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to make permanent 43 of the 45 sub-surface electric vehicle charging points installed under the STEP trial scheme, note the removal of two charge points in Parliament Hill, and delegate further decision-making authority to the Director of Environment and Sustainability.

Full council record
Purpose

To consider and make a decision on officer recommendations for
the future of Subsurface Technology Electric Pathways (STEP) charge
points beyond the trial.

Content

Consideration was given to a report of
the Director of Environment and Sustainability.
 
DECISION –
 
THAT, having considered the
results of the public consultation, the role of the provision of
accessible electric vehicle charging infrastructure in encouraging
the uptake of electric vehicles (thereby contributing to meeting
the objectives of the Camden Transport), the Equality Impact
Assessment detailed in Appendix C, and having had due regard to the
needs set out in section 149 of the Equality Act (2010), the
Cabinet Member for a Sustainable Camden is asked to:
 

   
i)              
Approve the making permanent of 43 of the 45 sub-surface
electric vehicle charging points, that were installed under the
STEP trial scheme in April 2022;

  
ii)             
Note that two of the 15 charge points initially installed in
Parliament Hill were removed due to the implementation of a rain
garden; and

 
iii)             
Delegate authority to the Director of Environment and
Sustainability to take any further decisions required on the
scheme.
 
 
Reasons
For the reasons set out in the
report.

Supporting Documents

Appendix C - EQIA Trojan Energy charge points.pdf
SMDReport 19Dec23.pdf
Appendix A Website Page for Consultation.pdf
Appendix D - Map of Trojan Energy EV Charge Point Installations.pdf
Appendix E - Legal Comments of the Borough Solicitor.pdf
SMDDecisionSheet 19Dec23.pdf
SMDagenda 19Dec23.pdf
Appendix B - EV Charge Points Consultation Postcard.pdf

Details

OutcomeRecommendations Approved
Decision date19 Dec 2023
Subject to call-inYes