International Sports Village
July 10, 2025 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Cardiff Council Cabinet approved the introduction of a car parking charging regime at the International Sports Village site based on Option 4 of the report, subject to securing required budgets. They also agreed to the evaluation criteria for the Energy Strategy and approved a procurement process for its delivery, delegating authority for the procurement process to the Director of Economic Development. Additionally, Cabinet approved Heads of Terms to enable the delivery of a primary sub-station at the ISV site and delegated authority for associated legal and financial matters to the Director of Economic Development.
Full council record
Purpose
To provide an update on the Cardiff International Sports Village (ISV) including an update on the parking strategy.
To set out a financial plan for delivery of the wider development.
Decision
Appendices 2, 5 and 9 of this report are not for publication as they contain exempt information of the description contained in paragraphs 14 and 21 of Schedule 12A of the Local Government Act 1972.
Appendices 7 and 10 of this report are not for publication as they contain exempt information of the description contained in paragraph 16 of Schedule 12A of the Local Government Act 1972.
Cllrs Ash Lister and Lynda Thorne declared a personal interest in this item as they are Ward Members for Grangetown.
RESOLVED: that
- the introduction of a car parking charging regime at the ISV site based on Option 4 of the report attached at Appendix 3 be approved subject to securing the required budgets as outlined at Confidential Appendix 9.
- the Evaluation Criteria set out in Confidential Appendix 2 be agreed and the implementation of a procurement process to deliver the Energy Strategy set out in the report and at Confidential Appendix 2 and Confidential Appendix 7 be approvedand authority be delegated to the Director of Economic Development in consultation with the Cabinet Member for Investment and Development, Section 151 Officer and Monitoring Officer to deal with all elements of the procurement process with the final negotiated terms, reported back to a future meeting of Cabinet for approval.
- the HOTs to enable the delivery of a primary sub-station at the ISV site as set out at Confidential Appendix 10 be approved and authority be delegated to the Director of Economic Development in consultation with the Cabinet Member for Investment and Development, Section 151 Officer and Monitoring Officer to deal with all associated legal and financial matters.
Related Meeting
Cabinet - Thursday, 10th July, 2025 2.00 pm on July 10, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 10 Jul 2025 |
| Effective from | 24 Jul 2025 |
| Expected date | 17 Jul 2025 |
| Originally due | 17 Jul 2020 |
| Subject to call-in | Yes |