Summary

The Cabinet of Cardiff Council decided to approve recommendations regarding the Coastal Risk Management Programme on 17 September 2026. They noted the scheme's progress, approved a contract programme extension and sectional completion for the rock armour area, and delegated future contractual changes to the Director of Frontline Services.

Full council record

Decision

Appendix 1 of this report is exempt from publication pursuant to of schedule 12A Part 4 paragraph 16 of the Local Government Act 1972 (as amended)

RESOLVED: that

  i.   the latest position on the Cardiff Coastal Protection Scheme be noted, including programme progress, key delivery challenges, financial position and projected outturn.

 ii.   the contract programme extension be approved.

iii.   sectional completion for the completed rock armour area be approved.

iv.   the contract modifications implemented to date be noted.

 v.   future contractual changes be delegated to the Director of Frontline Services, in consultation with the Cabinet Member for Climate Change, Strategic Planning & Transport, the Section 151 Officer, the Monitoring Officer and relevant officers.

Related Meeting

Cabinet - Thursday, 17 September 2026 - 2.00 pm on September 17, 2026

Supporting Documents

2026-09-17 Coastal Risk Management.pdf

Details

ReferenceCall-ins0
OutcomeRecommendations Approved
Decision date17 Sep 2026
Subject to call-inYes