Final General Revenue & Capital Budget Proposals 2025-26 and Quarterly Budget Monitoring Report October-December 2024
February 18, 2025 Cabinet, Council (Other) Key decision Awaiting outcome View on council websiteFull council record
Purpose
To consider the recommendations
Decision
RESOLVED THAT: Cabinet recommends that Council:
- Approves the revised budget for 2024/25 which is reported as part of the budget monitoring process for 31 December 2024 in Section 6 and Appendix 17.
- Considers the budget assessment by the Section 151 Officer at Appendix 2 in agreeing the following recommendations.
- Approves the final budget proposals including a proposed council tax for the services provided by Cheltenham Borough Council of £244.79 for the year 2025/26 based on a Band D property (an increase of 2.99%), as detailed in paragraphs 9.1 to 9.6.
- Approves the savings / additional income totalling £1,130,000 and the budget strategy at Appendix 4.
- Approves the revenue growth items totalling £392,647 at Appendix 5.
- Approves the capital programme at Appendix 6.
- Approves the use of reserves and general balances and note the projected level of reserves, as detailed at Appendix 7.
- Approves the programmed maintenance programme at Appendix 8.
- Approves the Medium Term Financial Strategy (MTFS) detailed in Appendix 9.
- Approves the flexible use of capital receipts strategy as detailed in Appendix 10.
- Notes the Council position in relation to the Gloucestershire business rates pool for 2025/26.
- Approves the Pay Policy Statement for 2025/26, including the continued payment of a living wage supplement at Appendix 11.
- Notes the responses to the questions raised during the budget consultation in Appendix 12.
- Approves the proposed fees and charges schedule for 2025/26 at Appendix 13, subject to appropriate consultation where required.
- Approves the Minimum Revenue Provision Policy 2025/26 at Appendix 14;
- Approves a level of supplementary estimate of £100,000 for 2025/26 as outlined in Section 18.
Based on the information included in Section 15 of this report:
- 17. Approves the delivery of the Mobility Hub as a single-phase construction and increase the Councils commitment under the Development Funding Agreement to facilitate this change.
- 18. Notes that a single-phase delivery is forecast to generate a further £4.8m in land receipts to the Council.
- 19. Notes that despite an increased funding commitment under the Development Funding Agreement, this is more than offset by the provision of £20m in Levelling Up Funding; overall borrowing is circa £10.6m lower than previously approved.
- 20. Delegates authority to the Deputy Chief Executive (Section 151 Officer) in consultation with the Cabinet Member for Major Developments and Housing Delivery to finalise the terms of a Deed of Variation to the Development Funding Agreement.
Related Meeting
Cabinet - Tuesday, 18th February, 2025 6.00 pm on February 18, 2025
Supporting Documents
Details
| Outcome | For Determination |
| Decision date | 18 Feb 2025 |
| Effective from | 26 Feb 2025 |
| Expected date | 21 Feb 2025 |
| Originally due | 21 Feb 2025 |
| Lead officer | Gemma Bell |
| Subject to call-in | Yes |