Energy efficiency proposals for Leisure@Cheltenham
June 11, 2024 Cabinet, Council (Other) Key decision Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Cabinet, Council was recommended to approve capital investments for Leisure@Cheltenham on 11/06/2024. The decision approved £264,500 for LED lighting and £83,750 for pool covers. Authority was delegated to the Director of Finance and Assets to procure and award contracts and monitor implementation.
Full council record
Purpose
To consider the recommendations
Decision
RESOLVED that Council be recommended to approve that :
- 1. a capital investment of £264,500 to replace the existing lighting system in the leisure centre with LED technology is approved;
- 2. a capital investment of £83,750 from the Green Investment Fund to install pool covers across the building is approved;
- 3. authority is delegated to the Director of Finance and Assets (Deputy s151 Officer) to procure and award the contract for the installation of the equipment and monitor the implementation.
Supporting Documents
Details
| Outcome | For Determination |
| Decision date | 11 Jun 2024 |
| Expected date | 17 Jun 2024 |
| Originally due | 17 Jun 2024 |
| Lead officer | Gemma Bell |