Cherwell Futures Programme
October 7, 2025 Executive (Other) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to address a projected funding gap and prepare for Local Government Reorganisation, the Executive approved the Cherwell Futures Programme, prioritizing Planning, Environmental Services, and Customer Engagement, allocating £0.4 million for initial work and earmarking £1.1 million for future implementation, and endorsing a delivery model emphasizing in-house project management with external support as needed.
Full council record
Purpose
To agree the Case for Change and approve the
procurement of the transformation partner
Content
Resolved
(1)
That the Cherwell Futures Programme to prioritise the three key
areas of Planning, Environmental Services, and Customer Engagement
(Single Front Door), as the core focus for the next phase of work
be approved.
(2)
That the allocation from the Projects Reserve of £0.4 million
to fund initial support and preparatory work required for the three
prioritised areas noted in resolution (1) above, together with
transferring £1.1 million from the Projects Reserve to a new
Cherwell Futures Reserve for implementation and resource costs,
subject to Executive approval, as required by the Council’s
Reserves Policy, be approved.
(3)
That the proposed delivery model referenced in section 4 of the
report, which aims to bring more project management in-house to
reduce risk and maximise cost-effectiveness, using external support
only where necessary, be approved.
Related Meeting
Executive - Tuesday 7 October 2025 6.30 pm on October 7, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 7 Oct 2025 |
| Subject to call-in | Yes |