Officer Delegated Decision: Handforth Garden Village Business Case

April 25, 2024 Executive Director Place (Officer) Approved View on council website
Full council record
Purpose

Economy & Growth Committee at its meeting
on 26.01.24 delegated authority to the Executive Director Place to
carry out the necessary work to progress the Handforth Garden Village scheme in advance of
further decisions. The report contained information about the
Council’s strategy for delivering the Garden Village and its
approach to negotiating with 3rd parties and generating capital
receipts, which if shared would potentially harm the
Council’s financial position.
 

Content

To commission Jacobs via the Council’s
Highways Services Contract to provide two specific elements of
work.
 • ongoing
project management of the initial primary infrastructure works
(IPIW).
• specialist support leading to the award
of the Design & Build contract via Scape Framework, an agreed
design scope and the appointment of a designer.
 
The estimated cost of this is £107,695
 

Supporting Documents

ODR2 - Cover Report.pdf

Details

OutcomeRecommendations Approved
Decision date25 Apr 2024
Subject to call-inYes