Staveley 21 – Appointment of Stepnell on Stage 1 PCSA Contract
October 25, 2023 Service Director - Economic Growth (Other) Approved View on council websiteFull council record
Purpose
At the Staveley 21 Project Board (17th October
2022), the board agreed the implementation of the Staveley 21
project, along with a list of appointments which could be
progressed to support this implementation.
The funding for the work was secured through the Town Deal, which
has allocated £5.9m for the development of the Staveley 21
project.
Content
That the Service Director for Economic Growth
approves:
• The appointment of Stepnell on stage 1 of a two-stage design
and build route on the basis of a pre-construction services
agreement (PCSA) at a cost of £365,806.
• That a letter of intent be issued to Stepnell for half of
their proposed RIBA stage 3 costs (£65,490.59)
Details
| Outcome | Recommendations Approved |
| Decision date | 25 Oct 2023 |