Period 2 Budget Monitoring Report 2024/25
July 16, 2024 Cabinet (Cabinet collective) Key decision Approved View on council websiteFull council record
Content
*RESOLVED –
1.
That the forecast outturn position of the General
Fund Revenue Account for the financial year 2024/25 be
noted.
2.
That the General Fund Capital Programme expenditure
forecast for the financial year 2024/25 be noted.
REASONS FOR RECOMMENDATIONS
1.
This periodic monitoring report
summarises the current assessment of the Council’s forecast
outturn position for the financial year 2024/25 and sets out the
active management mitigations being progressed to balance the
2024/25 budget. It also provides a robust basis for medium term
financial planning.
2.
This is the first formal monitoring
report for the 2024/25 financial year.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 16 Jul 2024 |